NEWS 02

                                                             Last updated: August 3Oth, 2026

On the 30th of June 2026 we received the Registration Certificate from Zambia Development Agency (ZDA), confirming our 35 MWac Solar Project in Chisamba District as a critical infrastructure project. 

Another milestone was reached on the 27th of July 2026, when the Grid Connection Agreement with Zambia Electricity Corporation (ZESCO) was signed. The Implementation Agreement with the Ministry of Energy is currently being reviewed by the Attorny General and is expected to be signed in September 2026.
 

 

NEWS 01

Last updated: May 15th, 2026

During the last few weeks, our Solar Project achieved several critical milestones. The Feasibility Study was approved by the Ministry of Energy on the 20th of April 2026. 

Only 2 weeks later, on the 6th of May, we received the “no objection letter” from ZEMA (Zambia Environmental Management Agency) regarding the Environmental and Social Impact Study. Final approval is expected in July 2026. 

Finally, the Grid Impact Study was approved by the Zambia Electricity Supply Corporation (ZESCO) on the 12th of May. 

The speed and efficiency of the relevant authorities and agencies in processing these approvals is a testament to the successful implementation of the new Zambian energy policies.

©Urheberrecht. Alle Rechte vorbehalten.

Information icon

Wir benötigen Ihre Zustimmung zum Laden der Übersetzungen

Wir nutzen einen Drittanbieter-Service, um den Inhalt der Website zu übersetzen, der möglicherweise Daten über Ihre Aktivitäten sammelt. Bitte überprüfen Sie die Details in der Datenschutzerklärung und akzeptieren Sie den Dienst, um die Übersetzungen zu sehen.